Reordering of Holy Trinity Church (5)
David Gill writes: We are at the end of week 5 and here are some photographs taken over the last few days. They show the stone floor slabs now laid in the entrance area and also against the left side book case. The kitchen servery is also shown as beginning to emerge. We are still on track to complete on 12th December.