Programme of Upcoming Works 04.04.22

  • w/c 4th April – Fencing works along boundary with High Rock to begin.

  • 9th May – Existing lamppost adjacent to new site entrance to be removed and relocated.

  • w/c 9th May – Overhead BT cable to front of site to be grounded.

  • w/c 16th May – foul water connection in main road outside site to be made.